Drung Jung Road upgrades underway

Published on 08 September 2020

Drung-JungRoad_20200901_085438_square.jpg

Stage 1 of works planned for Drung Jung Road are well underway, with 2 kilometres of road being upgraded.

Drung-JungRoad_20200907_084631_square.jpg

This week the contractor has been preparing a sub-base of orange gravel, over which class 1 FCR (fine crushed rock) will be spread.

Drung-JungRoad_20200907_083107_resized.jpg

Works are progressing well and this stretch of road should be sealed and completed within 3 weeks. 

The Drung Jung Road upgrade is jointly funded by Regional Roads Victoria and Horsham Rural City Council. 

 

 